Progress for New Floating Marina

Last month saw the installation of a new pontoon access bridge which will form part of the new access arrangements for the new marina. A major milestone in the development it is currently in a temporary position until it can be moved to its designated location.

Measuring over 25m in length and 2m wide it will make the incline at low water much more manageable for customers pushing full trolleys up the ramp after a day out on the water. 

Andy Osman CMM, General Manager comments: “We have already seen great progress on the redevelopment of Noss on Dart this year and despite some poor weather it has not delayed the works or the project timetable. The introduction of the new bridge now gives us the opportunity to finally remove the old structure which will complete the removal and demolition of the last of the old marina and bridgehead layouts. At this point, 109 new pontoon berths have been completed with work progressing by the day to get the rest of the marina completed by the spring.”