☰  Menu

News

New Car Park Extension for Berth Holders

13th October 2020

As the construction works at the marina progress, we have taken steps to ensure that our berth holders and marina visitors continue to enjoy good parking provision by extending our Woodland Car Park.

This extension has opened up a new area of parking, situated as close to the heart of marina as is possible at this time, and which will remain open for the duration of the development project watch out for the new signage that identifies this new car park.

Whilst a proportion of the main marina car park will remain in use for berth holders, a small section of parking is now dedicated to accommodating the construction vehicles and equipment being used for the renewal of the floating marina.

UPDATE – Construction of New Floating Marina

13th October 2020

Premier Marinas is delighted to announce that the construction of the new floating marina at Noss on Dart Marina has begun. 

Walcon Marine is now onsite and have started the phase 1 demolition and construction works, including the installation of the new inner walkways and what will become pontoon E and part of pontoon J. Once this phase has been completed, the marina team will temporarily relocate some berth holder boats onto the new sections whilst the Walcon team remove parts of the old pontoon to make way for phase 2, which will involve the construction of pontoons F and G.

Following this, the next major phases of the project will include: phase 3 – the construction of pontoons H and J; phase 4 – the construction of the additional walkways, which will ultimately lead to Premier’s dedicated water taxi and fuel pontoon berth; and phase 5 – the construction of pontoons A, B, C and D. The new £3.5m floating marina will provide a finger pontoon for each boat and rafting out will be a thing of the past.

Exciting Times For The Redevelopment Project

27th August 2020

Premier Marinas is excited to announce the next three major phases of the redevelopment project at Noss on Dart Marina are now underway. With an investment of £6.5m from Premier, this major milestone of the Noss redevelopment project includes Phase 5: the new stacked car park; Phase 6: the new water treatment plant; and Phase 7: the new commercial building.

The works commenced at the start of August and are being carried out by three different external contractors: Devon Contractors, Teignmouth Maritime Services and Gilpin Demolition, who have almost finished the demolitions works to clear the foundations of the old onsite buildings.

Andy Osman CMM, General Manager at Noss on Dart Marina said: “We are delighted to be working with these local construction companies and these new phases mark a landmark point in time when we really start to forge ahead with our plans.”

Phase 5 of the redevelopment project comprises the build of the new stacked car park, which will include 6 parking levels with 195 spaces dedicated for berth holders and guests from the new hotel/apartments. This park will only be accessible via key fobs for security and privacy.

Phase 6 involves the construction of the new water treatment plant at Noss on Dart Marina, which will manage all waste and brown water that the future site will generate from the hotel and residential properties. The first phase of the new water treatment plant will need to be operational for the new commercial buildings, which are currently planned to be open by September 2021.

The new commercial buildings are Phase 7 of the redevelopment project and will include seven units initially to be used by current tenants, South Devon Marine Academy, as well as other marine related commercial businesses and potentially a self-store. This stage of the project will also include the old slipway to be filled in to create the new revetment.

Phase Two Demolition Works Begin

22nd July 2020

External contractors, Gilpin Demolition have begun Phase 2 of the demolition works at Noss on Dart Marina, which involves clearing the foundations of the old onsite buildings, which the team were previously contracted to knock down.

Phase Two Demolition Works Begin

This phase of the redevelopment project involves digging up and crushing the existing concrete and old bricks, which will then be used to raise levels across the site, ahead of the construction of the new planned buildings in the future.

Andy Osman CMM, General Manager said: “We are pleased to welcome Gilpin Demolition back onsite to undertake the next phase of the demolition operations. This is a small but vital stage in the redevelopment of Noss and it is great to see the site starting to change and transform into Premier’s vision for the future.”

Andy adds: “The Gilpin team plan to be on site until mid-August, during which time we will do our very best to keep the dust levels under control at all times.”

New Substation For Noss On Dart Marina

1st July 2020

Noss Substation

Premier Marinas is delighted to announce that work has commenced on the construction of a new electricity substation at Noss on Dart Marina; part of a £75m redevelopment to make it the UK’s finest marina and boatyard.

The sub-station works are being undertaken by UK Power Solutions, who moved onto site in April. Works are now underway to construct the foundations required to house the new switch room, auxiliary transformer and a 14m telecommunications pole, in accordance with the approved planning consent for this important phase of the development. The UK Power Solutions team is adhering to all safe working and social distancing practices whilst on site.

Before the new transformer is energised and ready for use, a new electricity supply will be taken from the overhead HV cables to the top of the Noss on Dart site and fed under the main road. This supply will then run into the new services ducting, which leads to the new sub-station – both of which will be created as part of this project.

Andy Osman CMM, General Manager said: “This new substation is an essential upgrade to the local network and will see the marina benefit from a more robust and resilient electricity supply to meet the demands of customers requiring connections in the future”.

Due to the complex nature of the project and with the delayed start due to COVID-19, Premier Marinas anticipate that works will be complete by September.

Piles Trial Programme

27th March 2020

This month external contractors, Walcon Marine are on site with their piling barge the “Walcon Wizard” to test drive new piles in strategic locations across the footprint of the new floating marina in order to gain a much better understanding of the ground in which the new marina piles will be driven to create the new marina.

The current floating marina is held up by 14 piles which will increase to approximately 100 piles driven into the river bed, once the new marina is developed.

Andy Osman CMM, Marina Manager explains further: “We have no knowledge of how hard or soft the ground is and so this trial programme is necessary to make sure we are happy with the ground conditions. Works commenced on Monday 16th March and this marks a significant step forward for the marina redevelopment as a whole.”

Noss Piles Trial

Dredging To Be Completed End Of March

19th March 2020

The Noss on Dart team is pleased to announce that dredging will be completed by the end of March in line with planning consent. The dredging programme has been undertaken by Dutch dredging company, Royal Smals who are extremely experienced in projects of this light. The dredging was originally scheduled to begin in October 2019 but all the necessary permissions were not in place by that time.

Marina Manager, Andy Osman CMM said: “The dredging project has been very challenging for our contractors who have had to battle with severe weather conditions throughout February, with gale force winds and the wettest recorded since records began. However, good progress has been made with the project and we are on schedule to complete before the end of March.”

Dredging To Be Completed End Of March

Old Timber Quay Demolition

24th July 2019

Work on the Noss on Dart Marina regeneration is continuing with the removal of the old timber quay in anticipation of the reclamation of the land which will facilitate the construction of the new boatyard, Marina Reception and waterside apartments along the foreshore.

This work was completed in June with the deck section and timber piles removed, and a line of yellow marker buoys installed to mark the line not to cross in case of any underwater obstructions towards the land. The old Boatyard Office has also now been removed, but there is a section of the old timber piles kept in place for the time being to support the access ramp and bridge onto the pontoons. The access ramp and bridge will stay in position until phase 1 of the new floating marina starts. This phase is planned to start in October 2019.

Noss on Dart Marina RegenerationNoss on Dart Marina RegenerationNoss On Dart Old Timber Quay

Noss On Dart Marina Regeneration Updates

10th June 2019

Noss on Dart Marina Regeneration

The next phase of the regeneration of Noss on Dart Marina will see the removal of the old timber quay that meets the water’s edge by the marina bridgehead. This is being demolished in preparation for the installation of the new floating marina that will start construction later in the year.

This work will also involve the removal of the old Boatyard Marina Office portacabin. With this cabin now closed and awaiting removal, Noss on Dart Marina has amalgamated all administration operations under one roof in the Marina Reception where all bookings, payments and information will be serviced until further notice.

The removal of the old timber quay will help facilitate the reclamation of the land which will host the development of the new boatyard and other buildings along the foreshore, including the new Marina Reception and waterside apartments.

Dart Valley Trail Car Park Re-Opening

13th May 2019

Dart Valley Trail Car Park Re-OpeningToday Noss on Dart re-opened the Dart Valley Trail car park for the use of all dog walkers and other walkers who simply enjoy rambling through the beautiful trails through the woods at Noss.

The new car park has been part of the overall redevelopment of Noss on Dart Marina and represents a significant investment at an early stage of the project.  This morning Mrs Lesley Giles, her son and two dogs joined Andy Osman, General Manager at Noss Marina, along with other members of the Noss staff to formerly cut the safety ribbon to the new car park officially opening the new facility for use.  Lesley, a local resident, brings her dogs to Noss most days and welcomes the new facility which she says is a fantastic improvement on the old arrangements and particularly likes the new trees and general planting which is already improving the atmosphere and overall ambience of the site.